The Wings Diegem
Edge formwork with integrated edge protection for Ghelamco
For the prestigious The Wings office project in Diegem, GSS supplied the complete edge formwork with integrated edge protection. One system, one operation, allowing a single worker to continue safely on the next slab immediately.
Over the course of one year, 45,000 m³ of concrete was poured and 5,000,000 kg of steel was processed. A pace that can only be achieved with an edge protection solution that is quick to install, reusable and ensures site safety from the very first metre.
We will come to your site.
A technical advisor will visit with a GSS sample and show you in 30 minutes how the system works and where you can save time on installation. Free, no-obligation, and coordinated with a site foreman on location

No brochures or technical data sheets, just a real-life demonstration of the system at your location.

Floor thickness, substrate, connections, and specific site conditions are reviewed together.

You will receive a concrete quote within one working day of the visit.

Our consultants each have over ten years of site experience and understand the challenges. You will get answers, not a brochure.